We’re excited to share that the first three AOVs are
nearly complete!
The cabling and new structural frames are in place, and testing is underway to ensure the
mechanical systems that operate the vents are working perfectly. Once final checks are finished, these AOVs will be up and running, and the surrounding scaffolding will be taken down.
With this progress, ACSL is ready to refurbish the
remaining AOVs on Barandon Walk. At the same time, preparations are underway to start the roof
refurbishment projects on Testerton Walk and Hurstway Walk, where AOVs will also be upgraded.
The refurbished AOVs will bring improved ventilation and fire safety to the buildings, and the modern technology will make them more reliable. Plus, they’ll tie in with the broader roof upgrades, which will boost the buildings’ energy efficiency.
Thank you to the residents of the Walkways for your cooperation as we continue these roof improvement works.